Gym Floor Resurface/Paint
- What
- Gym Floor Resurface/Paint
- When
- 12/16/2022 – 1/3/2023
- Where
- Gym
12/16 - Half day possible YES AFTER 12N-5P (MARCOS/TINA)
12/19 - Start sanding Verde needs gym access to closet/office lighting (MARCOS/TINA)
12/20 - Continue sanding (MARCOS/TINA)
12/21-Finish sanding/layout and water pop for stain (MARCOS/TINA)
12/22-Stain (MARCOS/TINA)
12/23-Stain (MAX)
12/24-2 seal coats (If they want to work, which I feel like they would since it isn’t a long day) (MAX)
12/26-Any way they can work if they want to? (NO, office closed, everyone out)
12/27- Prep floor and start layout of game lines and letters (MARCOS/MARIO)
12/28-Continue layout (MARCOS/MARIO)
12/29-Prep and paint everything (MARCOS/MARIO)
12/30-Prep and coat #1 (MAX)
12/31- Final coat in the morning (Is this date possible?) YES (MAX)
1/1 - Cure day
1/2 - Cure day
1/3 - Cure day teachers in school
1/4 - Floor re-opens